Location: Winnipeg, Manitoba

Project Goal:

Urgent demolition of the fire-damaged Kirkwood Block building to ensure people’s safety and allow safe passage of vehicles within the vicinity took place last February 3, 2022 at Portage Avenue, Winnipeg.

Scope:

Our team dismantled the double billboards located on the roof of the building. We also demolished the remaining exterior walls in order to prevent from further collapse.

Number of Crew Involved with the Project:

4 men

Duration:

Our team started to mobilize at 3pm and completed the job with demobilization at 1 in the morning.