Material Recycling

September 12, 2017

Pine Ridge Building

Conventional Demolition, Hazardous Waste Removal, Material Recycling

The project involved the selective interior demolition of the historical Pine Ridge Building in Brandon, Manitoba. Over 300 tons of brick, concrete and steel were removed by hand. The basement area was heavily contaminated with mould...

No comment0
September 12, 2017

Atomic Energy of Canada

Conventional Demolition, Material Recycling

AECL had planned to decommission its nuclear facility in Pinawa, Manitoba, over a 10-year period but sped up plans significantly and in the summer of 2008, Rakowski demolished the first set of buildings. The project went extremely...

No comment1
September 11, 2017

James Richardson International Airport Terminal

Conventional Demolition, Hazardous Waste Removal, Material Recycling

Remediation and demolition of the old James Richardson International Airport Terminal building. The project involved 5 months of intensive asbestos abatement followed by the building demolition. with some 10 thousand tons of scrap metal ...

No comment2
September 11, 2017

Winnipeg Arena

Controlled Blasting, Conventional Demolition, Material Recycling

The arena, once home to the Winnipeg Jets NHL team, took five months to demolish with the main arena section of the building coming down with explosives. Over 5,000 tons of scrap was processed on-site and hauled away....

No comment0
September 11, 2017

Cargill Inland Grain Terminal

Controlled Blasting, Hazardous Waste Removal, Material Recycling

Remediation and demolition of a 11 story inland grain terminal. The project involved the remediation of asbestos, PCB and contaminated soils from the site. The main terminal building was prepared for explosive demolition and detonated Oc...

No comment3
September 11, 2017

Hudson Bay Mining & Smelting

Controlled Blasting, Hazardous Waste Removal, Material Recycling

Project involved the demolition of two headframes and the associated hoist rooms. Both included extensive asbestos remediation and environmental cleanup. The structures with a height of over 200 feet successfully brought to the ground wi...

No comment1

Our Projects

  • Controlled Blasting
  • Conventional Demolition
  • Hazardous Waste Removal
  • Material Recycling

consulting services


We provide consulting services to contractors or supply complete, start-to-finish implosions. We work closely with consulting engineers to perform pre-blast surveys and seismic monitoring.

CONTACT US

© Copyright 2017 Rakowski Cartage Winnipeg Wordpress Web Design -  Hello Digital MarketingManaged WordPress Hosting & Support - Hello Hosting
Image
© Copyright 2017 Rakowski Cartage
Image
  • Home
  • Services
    • Consulting Services
    • Controlled Blasting
    • Demolition
    • Hazardous Waste Removal
    • Recycling
  • Safety
  • Projects
  • Gallery
  • About
  • Contact
  • Rakowski Recycling